Sunday, January 10, 2010

It's a confimed MISTAKE!

Today is a good day, and today is a good start of a new year.

I have finally made up my mind to confirm, getting my first contractor was a total MISTAKE!

My new contractor has show me his word, his team of worker has completed a 2 days worth of job, which in my experience (yes I have lots of experience to how much work my 1st contractor can do), will take my 1st contractor weeks to do.

I do not want to blame anyone for this, but I want to learn everything I can from this MISTAKE, including as much knowledge I can get from building a house from ground up.

Keep up the good job Mr. Soon.

F off, Mr Francis.

Good night,
Ed

Wednesday, January 21, 2009

20090120: Updates

2nd corridor for Master Bedroom...


Kitchen, emmm....



Main Entrance with a 6 feets door.

Sunday, December 14, 2008

Project Updates: 20081213


The split level plaster ceiling is looking like not 'deep' enough woh~

New pipes are being installed and old pipe are being removed...





My 'Home Office'...


Entrance looking from inside.

Wednesday, December 10, 2008

On December 2008

To Do:
  1. Confirm Door Design - 1st Floor Children Room leading to Balcony. (Done 12/12/08)
  2. Confirm Door Design - Grd Floor Dinning Room leading to Garden. (Done 12/12/08)
  3. Confirm Door Design - Main Entrance. (Done 12/12/08)
  4. Confirm Toilet Design - Grd Floor Common.
  5. Confirm Toilet Design - 1st Floor Common.
  6. Confirm Toilet Design - 1st Floor Master.
  7. Confirm Mixer Tape Design.
  8. Confirm Shower Tape Design.
  9. Confirm Shower Room Design.
  10. Confirm Toilet Floor Design.

To Buy:
  1. Order more door frame. x2 SL x1 DL. (Done 12/12/08)
  2. Order Woodern Door. x1 DL. x5 SL.
  3. Order Aluminium Door. x2 SL. x1 Folding. (Done 12/12/08)
  4. Order Toilet Bowl. x3 Units. (Done 12/12/08)
  5. Order Basin Sink. x3 Units. (Done 12/12/08)
  6. Order Mixer Tape. x3 Units.
  7. Order Shower Tape. x3 Units.
  8. Order Shower Room.
  9. Order Toilet Floor Tiles.

Contractor Job List:
  1. Complete all plaster ceiling concealing job.
  2. Complete wall wire concealing job.
  3. Complete all windows frame skirting job.
  4. Complete all toilets piping job.

Friday, November 28, 2008

Project Updates: 20081128



Wiring is in place, waiting for Plaster Ceiling...

First Floor main switch.

Children's Room main window.


'Kayu Kabur'


Master Bathroom with open roof, haha~ only for now...

Looking down from Master Bedroom, this is gonna have a 

Heavy repairment going on at outside the Master Bedroom...

Ground Floor Main Switch...


Like a bunch of snakes, coming out from the base...


A hose for the main Air-Conditionaer...

Saturday, November 15, 2008

Things i learned from this round and what I need to pay attention to my 2nd house...

  1. Windows Frames:
  • When apply, need to make sure they are level properly.
  • Plastic covering need properly secured, to prevent cement powder from entering.