Today is a good day, and today is a good start of a new year.
I have finally made up my mind to confirm, getting my first contractor was a total MISTAKE!
My new contractor has show me his word, his team of worker has completed a 2 days worth of job, which in my experience (yes I have lots of experience to how much work my 1st contractor can do), will take my 1st contractor weeks to do.
I do not want to blame anyone for this, but I want to learn everything I can from this MISTAKE, including as much knowledge I can get from building a house from ground up.
Keep up the good job Mr. Soon.
F off, Mr Francis.
Good night,
Ed
Sunday, January 10, 2010
Wednesday, January 21, 2009
Sunday, December 14, 2008
Project Updates: 20081213
Wednesday, December 10, 2008
On December 2008
To Do:
- Confirm Door Design - 1st Floor Children Room leading to Balcony. (Done 12/12/08)
- Confirm Door Design - Grd Floor Dinning Room leading to Garden. (Done 12/12/08)
- Confirm Door Design - Main Entrance. (Done 12/12/08)
- Confirm Toilet Design - Grd Floor Common.
- Confirm Toilet Design - 1st Floor Common.
- Confirm Toilet Design - 1st Floor Master.
- Confirm Mixer Tape Design.
- Confirm Shower Tape Design.
- Confirm Shower Room Design.
- Confirm Toilet Floor Design.
To Buy:
- Order more door frame. x2 SL x1 DL. (Done 12/12/08)
- Order Woodern Door. x1 DL. x5 SL.
- Order Aluminium Door. x2 SL. x1 Folding. (Done 12/12/08)
- Order Toilet Bowl. x3 Units. (Done 12/12/08)
- Order Basin Sink. x3 Units. (Done 12/12/08)
- Order Mixer Tape. x3 Units.
- Order Shower Tape. x3 Units.
- Order Shower Room.
- Order Toilet Floor Tiles.
Contractor Job List:
- Complete all plaster ceiling concealing job.
- Complete wall wire concealing job.
- Complete all windows frame skirting job.
- Complete all toilets piping job.
Friday, November 28, 2008
Project Updates: 20081128

Wiring is in place, waiting for Plaster Ceiling...
First Floor main switch.
Children's Room main window.
'Kayu Kabur'
Master Bathroom with open roof, haha~ only for now...
Looking down from Master Bedroom, this is gonna have a
Heavy repairment going on at outside the Master Bedroom...
Ground Floor Main Switch...
Like a bunch of snakes, coming out from the base...
A hose for the main Air-Conditionaer...
Saturday, November 15, 2008
Things i learned from this round and what I need to pay attention to my 2nd house...
- Windows Frames:
- When apply, need to make sure they are level properly.
- Plastic covering need properly secured, to prevent cement powder from entering.
Tuesday, November 4, 2008
20081104: Ceiling and Partitions updates
My windows taking shape finally~
Saturday, October 25, 2008
20081025: Windows are partially ready...

Wall lights for the stair case...
Plaster Ceiling frames are up, too! Since the roof support beams have been removed, now the ceiling has been raise 1 feet upward, thus increase the spaciousness of the rooms.
Rooms partitions...
Tags
1st Floor,
Electricity,
Ground Floor,
Interior
Wednesday, October 15, 2008
Budget Again!!!
My redoing of all electricity is another slightly below RM10K!! Aarrrrrrrggggghhhhhh!
Tuesday, October 14, 2008
Monday, October 13, 2008
Wednesday, October 8, 2008
Project Updates: 20081008
Pending:
1. Quotation from Francis for:
1. Quotation from Francis for:
- Car Pouch Leveling Concrete.
- Gate Poles and concrete surrounding wall.
- Special concrete design poles for entrance and Brunch Area.
- 1st Floor Toilet Roofing.
- All Window Frames and Windows.
- All Door Frames & Doors.
- All Electricity Wiring Works.
Friday, September 26, 2008
Just paid another RM5,000 this morning...

That means I have only paid RM10,000 altogether, and Hari Raya is coming so another week will be no work. I have made it clear to the contractor this time starting October 2008 I will be the Project Manager for him. I will be responsible for making sure he meet hsi deadline for eacj stage of the work.
This is coming next for Octorber:
1. Complete the replacement job for the 2 Roof Support Beams from weak concrete to Stainless Steel.
2. Complete the final touch up concrete work for all Windows and Doors. Provided the Windows & Doors arrived on time.
3. Complete the hacking and replastering work for all weak concrete.
4. Clean up all debris and ready for the Electricity Work to start. Electricity Work will scheduled to start on 15/10/2008. (One day before I depart for Japan.)
5. Etc.